Parks Maintenance Notices

Posted on: August 6, 2019

Beaver Creek Greenway

We will be repairing bridges throughout the Beaver Creek greenway starting on Monday, August 19th.  Weather pending this project will last approximately 2 weeks.  Please be aware that during this time as repairs are made there will be no through traffic allowed in the areas being maintained. The work will begin at the Kelly Road entrance and we will work towards Jaycee Park.  After completion of the Kelly Rd. to Jaycee park section we will begin repairs at the Becketts Crossing section. If you have any questions or concerns please contact our front desk at 919-249-3402 and they will be happy to assist you.  